Key points
- Applied Digital signs an 18-year hyperscaler lease
- How the new lease's pricing compares
- Applied Digital closes a $300 million bridge facility
Applied Digital (APLD) signed an 18-year lease for 150 megawatts of data center capacity with an unnamed "tier-one investment-grade hyperscaler," the company said on Nov. 23. The lease adds about $5.4 billion of contracted revenue over its base term. Applied Digital shares were up 25.7% at $14.44 as of 10:13 a.m. ET, while CoreWeave (CRWV) was up 23.1%.
The lease could bring in about $12.7 billion if every renewal option is exercised over a 33-year total term, according to the release. Applied Digital's contracted base-term lease revenue now exceeds $41 billion, up from $36.2 billion in its fiscal 2026 annual report, the figure on our AI backlog tracker. With all renewal options, the total would be about $100 billion, the company said.
Delivery is expected to begin in the first half of calendar 2028, subject to development milestones, utility arrangements, and regulatory approvals. The release doesn't name the tenant or say which campus will host the capacity.
The new lease averages about 21% more per megawatt a year
Applied Digital said the lease has "improved commercial terms over our prior leases, including higher pricing." The release doesn't give a price, but its figures allow a rough comparison with the Delta Forge 2 lease that Applied Digital signed in June: 210 megawatts over 15 years for about $5.2 billion.
| New lease (Nov. 23) | Delta Forge 2 (June 8) | |
|---|---|---|
| Capacity | 150 MW | 210 MW |
| Base term | 18 years | 15 years |
| Base-term revenue | About $5.4 billion | About $5.2 billion |
| Average per year | About $300 million | About $347 million |
| Average per MW per year | About $2.0 million | About $1.65 million |
Sources: Applied Digital's Nov. 23 release and its Oct. 7 results release. The averages are base-term revenue divided by years and megawatts, and they ignore any rent increases built into either lease. The leases may also differ in services, costs, incentives, and payment schedules, so the comparison doesn't measure profitability or starting rent.
About 75% of Applied Digital's contracted base-term lease revenue now comes from investment-grade tenants, the company said. Its contracted critical IT load is now more than 1.6 gigawatts, with 2.2 gigawatts of grid-connected peak load.
Applied Digital plans to pay for it with Macquarie equity and project debt
Applied Digital will fund the build with equity from its balance sheet and its "$5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing," CFO Saidal Mohmand said in the release. He said the company expects to finish the remaining project financing for its Delta Forge 1 and Polaris Forge 3 campuses in the first calendar quarter of 2027, and for Delta Forge 2 in the second quarter. The release doesn't give a construction cost for the new capacity.
Fifteen minutes before the lease announcement, Applied Digital said it closed a $300 million senior secured bridge facility to keep building Delta Forge 1, its Louisiana campus. The 364-day loan carries interest at the Secured Overnight Financing Rate plus 3 percentage points. Draws depend on conditions that include construction milestones and state approval of electricity rates. Applied Digital said it expects to seek more financing to finish that campus.
In June, Applied Digital sold $1.59 billion of 7% notes due 2031 to fund a building at its Polaris Forge 1 campus in North Dakota and repay an earlier $300 million bridge facility. Applied Digital executives bought $6.7 million of stock in October, when the shares were at a one-year low.