CoreWeave (CRWV) letter to Texas leaves out its unbuilt capacity there. Galaxy (GLXY) filings show 393 MW to come.

CoreWeave logo on a white background above the words CoreWeave's letter to Texas skips its unbuilt capacity there, 393 MW still to come at Galaxy's Helios campus

Key points

  • CoreWeave's letter backs Hinojosa on power bills and water
  • CoreWeave doesn't say how much of its capacity is in Texas
  • Galaxy's filings show 393 MW still to come at Helios

CoreWeave (CRWV) chief executive Michael Intrator has told Texas Governor-elect Gina Hinojosa that the company will pay for its grid hookups and limit water use as it builds data centers. In a Nov. 7 letter, he said the company supports her principles for making data center growth "work for Texans."

The letter doesn't say how much of CoreWeave's planned capacity is in Texas or how much already has permits. TheStreet flagged those missing figures on Monday.

One landlord's filings show part of CoreWeave's planned Texas footprint. Galaxy Digital (GLXY) has leased 526 megawatts of critical IT load to CoreWeave at its Helios campus in Dickens County and delivered 133 MW. Of the remaining 393 MW, second-phase deliveries of 260 MW are scheduled to begin in the second quarter of 2027; rent for the third phase of 133 MW is scheduled to start in 2028.

Galaxy's filings don't say whether all of that remaining capacity has its permits and grid approvals.

What CoreWeave told Hinojosa

Hinojosa won the governor's race on Nov. 3 after calling for a pause on data centers. Intrator wrote to her four days later. Semafor reporter Ashley Gold posted the letter on X, and Bloomberg reported it the same day.

On power bills, Intrator wrote that CoreWeave funds "substations, transmission upgrades, and related buildout, so the costs of our growth are not passed along to neighboring households." On water, he said new capacity will use closed-loop liquid cooling and that "day-to-day water use is comparable to, or lower than, a commercial office building of similar size."

The letter lists active CoreWeave facilities in six places: Austin, Denton, Dickens County, Plano, Richardson, and Round Rock. Its capacity figures are company-wide. CoreWeave had "more than 1.5 gigawatts of active power" across 51 data centers as of June 30, and about 4.2 gigawatts of contracted power as of Aug. 11. The two figures carry different dates, so the gap between them isn't an exact count of unbuilt capacity.

Intrator closed by offering to work with Hinojosa's transition team "on the responsible completion of permitted projects and on clear, durable standards for future development." TheStreet's Opeyemi Babalola wrote that the line "skips everything in between," meaning projects still waiting for approval during a freeze. The letter doesn't say how many of CoreWeave's Texas projects, if any, are in that group.

Hinojosa's own words on permitted projects

The letter says CoreWeave "welcomed your clarification that currently permitted data center projects will be allowed to be completed." It doesn't say when or where she said that. The Next Web said it couldn't find Hinojosa saying it herself.

The closest public account is a Nov. 1 interview with Abilene station KTAB, two days before the election. The station reported that she said the pause would apply to new permits "rather than stopping projects already under construction." The station paraphrased her and didn't quote her directly. In an Oct. 22 video quoted by the Texas Tribune, she said she would issue "a moratorium — a ban — on all data center approvals" until the Legislature passes protections.

After the election, she told CNN that "we need to stop what we are doing with data centers until we have those protections." Nancy Sims, a political science lecturer at the University of Houston, told ABC13 that Hinojosa can only act on future data centers. "You can't really freeze mid-construction," she said. "What she can do is put a moratorium on new data centers."

Hinojosa takes office on Jan. 19. The Legislature convenes a week earlier, on Jan. 12.

How much CoreWeave capacity in Texas is still unbuilt

CoreWeave's filings don't break out its Texas capacity. Core Scientific and Galaxy report their CoreWeave sites, which cover three of the six locations in the letter.

SiteLandlordLeased to CoreWeaveDelivered so farStill to come
DentonCore ScientificAbout 260 MWAbout 260 MWNone reported
AustinCore ScientificAbout 20 MWAbout 20 MWNone reported
Helios, Dickens CountyGalaxy526 MW133 MW260 MW from Q2 2027, 133 MW in 2028

Core Scientific figures are leased and billing power from its Nov. 5 earnings deck. Galaxy figures are critical IT load from its Oct. 27 shareholder deck. No MW figures are disclosed for Plano, Richardson, or Round Rock.

Core Scientific (CORZ) is billing CoreWeave for all of the Texas capacity it leases to CoreWeave. Most of the CoreWeave capacity it isn't yet billing for is in Dalton, Georgia, due in early 2027. In its latest quarterly filing, the company said its exposure to delays in new Texas grid approvals "is limited with respect to the capacity covered by those agreements."

Critical IT load is the power available to the computing equipment itself. Galaxy's deck lists 800 MW of gross power capacity for the same CoreWeave lease. The 393 MW figure is measured in critical IT load.

At Helios, Galaxy said in its third-quarter results that the second phase "is fully financed and under construction," with data hall deliveries "scheduled to begin in the second quarter of 2027." Its shareholder deck puts that phase's annual base revenue at $675 million. The filings don't give the permit or grid-approval status of the second and third phases.

Texas already paused new grid hookups in August

Gov. Greg Abbott ordered an audit of data centers in Texas' grid connection line on Aug. 3. The grid operator, ERCOT, responded by pausing approvals to energize data centers of 75 MW or more. ERCOT's September board update says the pause covers large data centers not yet connected to its grid and lasts until the audit and a separate community impact review are done. ERCOT will file both reports with state regulators by Dec. 10, and its final decisions on which large projects stay in its connection study come in December. On Sept. 21, Abbott told the state's environmental agency to pause data center permits until ERCOT finishes its review.

Galaxy warned in its June-quarter filing that the audit "may impact the power approval timelines for certain of our data center sites." It didn't name the sites.

How CoreWeave stock has traded since the election

CoreWeave shares fell 9.9% on Nov. 4 and 9.8% on Nov. 5, then rose 6.3% to close at $46.40 on Nov. 6. Barron's reported early Monday that the stock was falling again before the open. By 12:05 p.m. ET, it was up 6.3% at $49.30.

CoreWeave's 9.625% notes due 2032 yielded more than 16% as of Nov. 6. The company reports third-quarter results after the market closes on Nov. 10.

Frequently asked questions

What did CoreWeave's letter to Gina Hinojosa say?

In a November 7, 2026 letter, CoreWeave CEO Michael Intrator told Texas Governor-elect Gina Hinojosa that the company supports her principles on data centers. He said CoreWeave pays for substations and transmission upgrades so the costs aren't passed to households, and that its closed-loop cooling uses about as much water as a similar-sized office building, or less.

How much of CoreWeave's Texas capacity is still unbuilt?

CoreWeave doesn't disclose a Texas figure. Its landlords' filings cover three of its six Texas locations. Core Scientific is billing for all of its roughly 260 MW in Denton and 20 MW in Austin. Galaxy has delivered 133 MW of 526 MW at its Helios campus in Dickens County, with 260 MW scheduled from the second quarter of 2027 and 133 MW in 2028.

Did Hinojosa say permitted data centers can be finished?

CoreWeave's letter says it welcomed her clarification that currently permitted projects will be allowed to be completed, but it doesn't say where she said it. Before the election, Abilene station KTAB reported that she said her pause would apply to new permits rather than projects already under construction. That was the station's paraphrase, not a direct quote.

Is there already a data center pause in Texas?

Yes. After Gov. Greg Abbott's August 3, 2026 directive, ERCOT paused approvals to energize data centers of 75 MW or more that aren't yet connected, pending an audit it will file by December 10, 2026. On September 21, Abbott told the state's environmental agency to pause data center permits until that review is done. Hinojosa takes office on January 19, 2027.

More on CRWV and GLXY

Latest stories

Dennis Singleton
Dennis Singleton

Dennis Singleton was born in Australia and later moved to the United States. He has spent years following the markets, but what keeps his attention is how AI is built. He writes about the companies behind the technology, from semiconductor designers and advanced packaging to photonics, memory, networking, and the hardware powering modern AI. His approach starts with filings, earnings, and industry research, then translates the important details into clear, straightforward analysis without unnecessary hype.