TeraWulf (WULF) signed a deal to double power at its Kentucky AI campus to 1 GW. No customer is named.

TeraWulf logo above the text 500 MW to 1 GW, Kentucky power deal

Key points

  • TeraWulf's amended agreement would double Muskie's contracted power
  • Power for the second phase could arrive a year earlier
  • The announcement names no Muskie customer

TeraWulf (WULF) has signed an amended power agreement that would double contracted capacity at its Muskie data center campus in Grayson, Kentucky, to 1 gigawatt from 500 megawatts. The agreement with Kentucky Power, an American Electric Power (AEP) company, still needs approval from the Kentucky Public Service Commission. The stock was up about 3% in premarket trading on Oct. 5.

The amendment would also move planned delivery of Muskie's second 500-megawatt phase to 2029 from 2030, depending on that approval and Kentucky Power's construction schedule. The first 500-megawatt phase is still targeted to begin ramping in 2028. Kentucky Power plans to file the amended contract and seek the related approvals later this year.

If the commission approves it, TeraWulf would fund $100 million in winter bill credits for Kentucky Power's residential customers over the first 10 years of the contract, the utility said. For a typical household, that could be about $25 a month during the winter heating season, starting in 2029.

"Customer interest in Muskie has been tremendous, and power availability is central to those conversations," Chairman and Chief Executive Paul Prager said. "Securing the next 500 MW and moving its planned delivery into 2029 gives us greater flexibility to meet prospective customers' deployment needs."

The announcement names no Muskie customer

Neither company's announcement names a tenant for Muskie. TeraWulf bought the site in May 2026 to develop as an AI and high-performance computing campus. Kentucky Power is developing a 765-kV/345-kV substation connected to the regional transmission network to serve it.

Muskie is a separate project from TeraWulf's Justified Data campus in Hawesville, Kentucky, where the company signed a 20-year lease with Anthropic in July. The Kentucky Public Service Commission approved the power agreement for Hawesville in August. TeraWulf said the commission found that its terms adequately protected existing customers.

TeraWulf is studying up to 2 GW

The company said it continues to evaluate Muskie's potential to support up to 2 gigawatts over time. That would depend on more utility planning, infrastructure and agreements. Development will follow Kentucky Gov. Andy Beshear's executive order on data center development, according to TeraWulf's release.

TeraWulf shares closed at $15.49 on Oct. 2. They traded at $15.98 in premarket trading at 8:45 a.m. Eastern on Oct. 5.

Frequently asked questions

What did TeraWulf announce about its Muskie campus?

On October 5, 2026, TeraWulf (WULF) said it signed an amended electric service agreement with Kentucky Power, an American Electric Power company, that would raise contracted power at its Muskie data center campus in Grayson, Kentucky, from 500 megawatts to 1 gigawatt. The agreement still needs approval from the Kentucky Public Service Commission.

When will TeraWulf's Muskie campus come online?

The first 500-megawatt phase is targeted to begin ramping in 2028. The amended agreement would move the second 500-megawatt phase to 2029 from 2030, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule.

Is Muskie the TeraWulf data center leased to Anthropic?

No. The 20-year Anthropic lease TeraWulf signed in July 2026 is at its Justified Data campus in Hawesville, Kentucky. The October 5 announcements name no tenant for Muskie, which TeraWulf bought in May 2026.

More on WULF

Dennis Singleton
Dennis Singleton

Dennis Singleton was born in Australia and later moved to the United States. He has spent years following the markets, but what keeps his attention is how AI is built. He writes about the companies behind the technology, from semiconductor designers and advanced packaging to photonics, memory, networking, and the hardware powering modern AI. His approach starts with filings, earnings, and industry research, then translates the important details into clear, straightforward analysis without unnecessary hype.