Data center power

Behind-the-meter data center tracker

Data center projects that run on their own power plant, a direct line to a power station, or on-site bridge power, instead of waiting for a grid connection.

44Projects listed
5Operating
12Under construction
7Countries

Updated · ledger as of Nov 27, 2026

More data center developers are building their own power instead of waiting years for a utility connection. This page lists each project we could confirm that gets its electricity behind the meter, with the companies involved, the plant's size, and where the project stands. Each row links to the filing, release, or report we read.

United States

Texas has the most projects on the list, followed by Ohio. Rows are sorted by status, then by size. Megawatt figures are what the source reports, and they don't all measure the same thing, so read the label under each one.

ProjectPowerStatusSource
Vantage San Antonio campusesSan Antonio, TexasVantage Data Centers, VoltaGridEnvironmental groups sued in federal court in September, saying the plants were split into smaller sources to qualify for less stringent permits. Their July notice put the gas plants at 423 MW, and the Sierra Club's September release says 405 MW.423 MW (405 MW in a later filing)Gas enginesOn-site plantOne operating, one under constructionAs of Sep 22, 2026Texas Public Radio
Second source
Socrates (Meta New Albany)New Albany, OhioWilliams (WMB), Meta (META)Williams built and runs the two 200 MW plants for Meta. It said on Nov. 2 that Socrates was fully online and that the second site, Plato North, was on track for service by mid-November.400 MW across two sitesGas turbines and enginesOn-site plantOperatingAs of Nov 2, 2026Ohio Power Siting Board
Second source
Equinix fuel cell fleet19 sites in six statesEquinix (EQIX), Bloom Energy (BE)About 75 MW was running and 30 MW was under construction as of February 2025. The fuel cells supplement grid power.More than 100 MW in totalFuel cellsOn-site plantOperatingAs of Feb 20, 2025Bloom Energy
Redwood Energy and CrusoeSparks, NevadaRedwood Materials, CrusoeSolar power stored in old electric vehicle batteries runs a 2,000-GPU modular data center that Crusoe describes as off-grid.12 MW, 63 MWhSolar and used EV batteriesOn-site plantOperatingAs of Mar 24, 2026TechCrunch
Second source
ECL MV1Mountain View, CaliforniaECL, LambdaThe Register reported a Lambda system there powered entirely by hydrogen fuel cells.About 1 MWHydrogen fuel cellsOn-site plantOperatingAs of Sep 24, 2025Data Center Frontier
Second source
Project Jupiter (Stargate New Mexico)Dona Ana County, New MexicoOracle (ORCL), Bloom Energy (BE)Bloom fuel cells replaced earlier plans for gas turbines and diesel generators. The hearing on the microgrid's state air permit was delayed again in November at the request of the developer and the state.Up to 2,450 MWFuel cellsOn-site plantData center under construction; power permit pendingAs of Nov 6, 2026Our report
Oracle
Second source
Project Phoenix (Aligned)Shippingport, PennsylvaniaAligned Data CentersAligned broke ground on Sept. 10 at the former Bruce Mansfield coal plant. It hasn't named its fuel cell supplier or said how much grid capacity the site keeps for backup.2 GW campusGas-fed fuel cellsOn-site plantUnder constructionAs of Sep 10, 2026Data Center Frontier
Second source
Joule campusMillard County, UtahJoule Capital Partners, Caterpillar (CAT)Joule told BloombergNEF that 455 MW is contracted for delivery by the end of 2026 and 1.5 GW by the start of 2028. The site's grid connection isn't big enough for the data center.1,500 MW first phaseGas enginesOn-site plantUnder constructionAs of Feb 27, 2026BloombergNEF
Second source
Colossus 2 power plantSouthaven, MississippiSpaceX (SPCX)Sixty-nine temporary turbines power the site until the 41-turbine permanent plant is finished; SpaceX says the temporary units will be gone by July 2027. A federal judge let the NAACP's lawsuit over the turbines proceed on Oct. 30.1,200 MW plantGas turbinesOn-site plantUnder constructionAs of Jul 30, 2026Our report
xAI
Second source
Meitner Energy CenterGray and Roberts counties, TexasAlphabet (Google, Intersect) (GOOGL)Google says the data center will come online alongside dedicated power. The gas units for firming are on site, and their size wasn't disclosed.More than 1 GW of renewablesWind, solar, batteries, and gasOn-site plantUnder constructionAs of Jun 4, 2026POWER Magazine
Second source
Crusoe Abilene campus for MicrosoftAbilene, TexasCrusoe, Microsoft (MSFT)Crusoe says the campus pairs a 900 MW on-site power plant with batteries, and the first building is due to be energized in mid-2027. It hasn't said what fuel the plant uses.900 MW plantNot disclosedOn-site plantUnder constructionAs of Jun 9, 2026Crusoe
Second source
Apollo (Meta Bowling Green)Wood County, OhioWilliams (WMB), Meta (META)Ohio's siting board approved the plant on Feb. 3, less than three months after plans were submitted, Reuters reported. The plant will serve only Meta.350 MW plus 120 MW of batteriesGas turbinesOn-site plantUnder constructionAs of Jun 16, 2026Ohio Power Siting Board
Second source
Project Aquila (Meta Eagle Mountain)Eagle Mountain, UtahWilliams (WMB), Meta (META), GE Vernova (GEV)City planning minutes describe a 286 MW plant separated from Rocky Mountain Power's system. Williams has since said Aquila will supply 520 MW under a 12.5-year agreement.286 MW in city filingsGas turbines, engines, and batteriesOn-site plantUnder constructionAs of May 7, 2026Eagle Mountain Planning Commission
Second source
Aalo microreactor and CrusoeIdaho National LaboratoryAalo Atomics, CrusoeA federal pilot program demonstration that plans to power a Crusoe modular data center in 2027.10 MW reactorSmall nuclear reactorOn-site plantUnder constructionAs of Jul 30, 2026POWER Magazine
Second source
Frontier (Vantage, Stargate)Shackelford County, TexasVantage Data Centers, VoltaGrid, Oracle (ORCL)An Oracle and OpenAI fact sheet says the campus is powered by an on-site, behind-the-meter gas microgrid using Jenbacher engines. Bisnow reported the 10-building campus at 1.4 GW and more than $25 billion.1.4 GW campusGas enginesOn-site plantUnder constructionAs of Sep 4, 2026Oracle and OpenAI fact sheet
Second source
GW RanchPecos County, TexasPacifico Energy, Amazon (AMZN)Amazon has confirmed it bought the site and plans to buy power from Pacifico, whose plant is designed to run off the grid. Amazon says it is exploring a later move to grid service, and the state's preliminary review describes a 5,000 MW plant.7,650 MW of gas in the air permitGas, solar, and batteriesOn-site plantApprovedAs of Aug 17, 2026Turbomachinery Magazine
Second source
Monarch campus (Nscale)Mason County, West VirginiaNscale, Caterpillar (CAT), Anthropic (ANT)Caterpillar and its dealer are due to deliver gas generators from September 2026 through August 2027, reaching 2 GW in the first half of 2028. Anthropic plans to use a 460 MW building at the campus.2 GW of generators contractedGas enginesOn-site plantState-certified microgridAs of Nov 2, 2026Our report
Nscale
Second source
CloudBurst San MarcosGuadalupe County, TexasCloudBurst Data Centers, Energy Transfer (gas supply) (ET)Texas regulators issued the plant's permit on Nov. 16, according to Public Citizen. The permit is in the name of Evolve Energy, which shares a chief executive with CloudBurst. Earlier reports described a 1,200 MW plant.1,605 MW in the state reviewGas turbines and fuel cellsOn-site plantApprovedAs of Nov 16, 2026Public Citizen
Second source
Prometheus HyperscaleEvanston, WyomingPrometheus HyperscaleUinta County approved the permit in June, and a judge dismissed a challenge in August. The company says the campus will run as a fully islanded microgrid.1,250 MW initialGas engines and turbinesOn-site plantCounty permit approvedAs of Oct 28, 2026Prometheus Hyperscale
Second source
Project Hummingbird (IEP)Greene County, PennsylvaniaInternational Electric PowerThe county planning commission approved the first phase, including two gas turbines, in December 2025. No tenant has been named.944 MW (local reports: 900 to 910 MW)Gas combined cycleOn-site plantApprovedAs of Dec 17, 2025Utility Dive
Freestone Energy Center and CyrusOneFreestone County, TexasConstellation Energy (CEG), CyrusOneThe Texas utility commission approved the arrangement in May with conditions that let the data center load be curtailed. Constellation says CyrusOne signed for 380 MW, with another 380 MW in a second phase.760 MW loadGas plantWired to a power plantApprovedAs of May 2026Texas PUC Docket 58872
Second source
Starbase supercomputing siteStarbase, TexasSpaceX (SPCX)SpaceX says it will invest more than $24 billion. Reports of the plant's size conflict: the application describes 35 turbines and 748 MW, while Public Citizen, citing state records, says the permit covers 43 turbines and 1,456 MW.748 MW in the permit applicationGas turbinesOn-site plantApprovedAs of Nov 16, 2026Our report
TechRadar
Second source
AWS Hilliard fuel cellsHilliard, OhioAmerican Electric Power (AEP), Amazon (AMZN), Bloom Energy (BE)AEP says the fuel cells let data centers start while the grid grows. The city of Hilliard filed an appeal of the Ohio EPA permit in November 2025.72.9 MWFuel cellsBridge until gridApprovedAs of Sep 22, 2025AEP Ohio
Second source
Cologix fuel cellsCentral OhioAmerican Electric Power (AEP), Bloom Energy (BE)Ohio regulators approved the 15-year contract on May 28, 2025. Cologix pays the full cost.Not disclosedFuel cellsBridge until gridApprovedAs of May 28, 2025AEP
Second source
Project Matador (Fermi America)Carson County, TexasFermi (FRMI)Fermi's Nov. 12 quarterly filing describes about 11 GW of planned private-grid generation and no signed tenant. Its hyperscaler deal is a non-binding letter of intent, and Texas Tech can end the land lease if it doesn't give a go-ahead by Dec. 31.About 11 GW plannedGas now, nuclear plannedOn-site plantProposedAs of Nov 12, 2026Fermi 10-Q
Second source
Project KilbyReeves County, TexasChevron (CVX), Microsoft (MSFT), GE Vernova (GEV), Texas Pacific Land (TPL)Chevron plans the plant to supply a Microsoft data center under a 20-year agreement, with first power targeted for 2028. It hasn't announced a final investment decision.2,670 MWGas turbinesOn-site plantProposedAs of Jun 23, 2026Oil & Gas Journal
Second source
Project Horizon (Poolside)West TexasPoolside, CoreWeave (CRWV)CoreWeave is the anchor tenant for the first 250 MW phase under a 15-year lease. The grid connection is for backup.2 GW campus in eight phasesGas turbinesOn-site plantProposedAs of Oct 29, 2025Data Center Frontier
Comanche Peak and AmazonSomervell County, TexasVistra (VST), Amazon (AMZN)Vistra's filing with the Texas utility commission says the Amazon load connects to the nuclear plant and is not expected to be served by grid power. Vistra's 10-Q calls it a 20-year, 1,200 MW deal starting in the fourth quarter of 2027.1,200 MW loadNuclear plantWired to a power plantAwaiting state approvalAs of Nov 25, 2026Texas PUC Docket 59399
Second source
PowerPlay AI and Sharon AIAbilene area, TexasPowerPlay AI, Sharon AI (SHAZ)The joint venture is still lining up gas supply and choosing a power producer.400 MW targeted by 2028Gas (type not chosen)On-site plantProposedAs of Jul 20, 2026PowerPlay AI
Second source
McCloud Generation (Meta El Paso)El Paso, TexasEl Paso Electric, Meta (META)The utility-owned plant would power the data center alone for five years, starting in 2027, and stay separate from El Paso Electric's transmission system. Meta pays the costs. We found no ruling yet from the state utility commission.366 MWGas enginesBridge until gridProposedAs of Apr 6, 2026Argus Media
Second source
CoreWeave in VoloVolo, IllinoisCoreWeave (CRWV), Bloom Energy (BE)Bloom said the fuel cells would be commissioned in the third quarter of 2025. We found no confirmation that they were.Not disclosedFuel cellsOn-site plantProposedAs of Jul 16, 2024Bloom Energy
Second source
Intel Santa Clara expansionSanta Clara, CaliforniaIntel (INTC), Bloom Energy (BE)Intel's site has run on Bloom fuel cells since 2014, and the 2024 deal expands it. We found no report that the expansion is finished.Not disclosedFuel cellsOn-site plantProposedAs of May 9, 2024Bloom Energy

Outside the US

The Japanese and South Korean projects take power directly from a power plant or wind farm. Most of the Canadian and Australian ones are new gas plants built for the campus.

ProjectPowerStatusSource
SK AI data center UlsanUlsan, South KoreaSK Telecom, Amazon (AMZN)SK Multi Utility, a local power provider, supplies electricity directly instead of the national utility, which serves as backup. The first 41 MW building is due by the end of 2027.100 MW of data center by 2029District power plantWired to a power plantUnder constructionAs of Sep 13, 2026Asia Economy
Second source
Pure DC Dublin microgridWest Dublin, IrelandPure Data Centres, WartsilaWartsila says the microgrid is designed to run completely independently from the national grid. Its first two energy centers, 30 MW each, were being commissioned.60 MW built, 110 MW plannedGas enginesOn-site plantBeing commissionedAs of Mar 12, 2026Microgrid Knowledge
Second source
Greenlight Electricity Centre (Meta Alberta)Sturgeon County, AlbertaPembina Pipeline (PBA), Meta (META)Pembina calls Greenlight a dedicated, behind-the-meter plant for Meta's data centre. It says the plant has all major regulatory approvals and is due in service in the second half of 2030.932 MWGas combined cycleWired to a power plantApproved; investment decision madeAs of Jul 8, 2026Our report
Pembina
Second source
Cloud Carrier Southern HighlandsMoss Vale, AustraliaCloud CarrierA second 16 MW unit was refused and is in court, and a separate state application seeks about 673 MW of gas generators to power the campus.14 MW approvedGas generatorsOn-site plant14 MW approved; more in court or proposedAs of Oct 7, 2025RenewEconomy
Second source
Herbata campusNaas, IrelandHerbataKildare County Council approved the campus in August 2025, and appeals lodged in September 2025 show no decision on the planning board's case page. An on-site gas plant would supply half its electricity, with wind and solar contracts covering the rest.Not disclosedGasOn-site plantCouncil approved; appeal pendingAs of Aug 20, 2025The Irish Times
Second source
Shelford data centre (Era4)Canterbury, EnglandEra4The site would take power by private wire from a landfill gas plant next door, with the national grid as backup. The council approved it on Oct. 15 by four votes to one, with three abstentions.Not disclosedLandfill gas plantWired to a power plantApprovedAs of Oct 15, 2026Construction Review Online
Second source
Wonder Valley (O'Leary Digital)Greenview, AlbertaO'Leary DigitalThe developer plans to file for provincial utility approval of the gas plant by the end of 2026. Sturgeon Lake Cree Nation has filed three court challenges.7.5 to 9 GW, by reportGasOn-site plantProposedAs of Nov 3, 2026BNN Bloomberg
Second source
Beetaloo Digital WeddellNear Darwin, AustraliaBeetaloo EnergyThe territory government made an exclusive commitment of more than 185 hectares of land to the project, which the company says could attract A$40 billion of investment.Up to 2 GWGasOn-site plantProposedAs of Jul 22, 2026ESD News
Second source
Project Ares (Energy North)Northern Territory, AustraliaEnergy NorthThe developer plans a fully off-grid campus that starts mainly on gas. A final investment decision is targeted 12 to 18 months after approvals.About 1,038 MW of gasGas, solar, and batteriesOn-site plantUnder environmental assessmentAs of Jul 22, 2026The Next Web
Second source
JERA Chiba power stationChiba, JapanJERA, Dell (DELL), RHAELM, Apollo (APO)JERA's Oct. 1 release says the project will draw power behind the meter from its operating plant, with investment expected to exceed $15 billion. JERA said on Nov. 27 it is in talks with Anthropic, Meta, and others about sites at its Tokyo-area plants.Up to 400 MWThermal power plantWired to a power plantProposedAs of Oct 1, 2026Our report
JERA
Second source
SGC AI data center GunsanGunsan, South KoreaSGC Energy, KT CloudSGC Energy plans to connect its power plant directly to the data center and keep access to the national grid. Asia Economy reported that full operation is slated for the first quarter of 2028.60 MW first phase, up to 300 MWPower plantWired to a power plantProposedAs of Sep 28, 2026Herald Business
Second source
Toyota Tsusho wind-farm data centerWakkanai, JapanToyota TsushoPower comes by private line from a 42 MW wind farm, not through the utility grid. Full operation is planned within 2027.3 MWWind farmWired to a power plantProposedAs of Jan 14, 2026Toyota Tsusho

The Senate bill on data center grid costs

The Senate passed the Bipartisan American Affordability and Jobs Act 62-33 on Nov. 19, 2026, according to the roll call. The bill would make data centers pay the grid costs they cause instead of other customers. It now goes back to the House, which has to act on the Senate's version.

The cost rules reach a data center site that is "supplied through electrical equipment that is connected to the bulk-power system," the passed text says. A campus that runs fully off the grid falls outside that definition. Some coverage of the bill described a 20 MW threshold, but the passed text sets none.

Projects we left out, and why

These projects are often described as behind the meter. The sources we read don't support that today.

ProjectWhy it isn't listedSource
SB Energy's Ports-Pike campus for OpenAIPike County, OhioPower comes through AEP Ohio's grid. OpenAI says the first 800 MW will largely use existing AEP infrastructure.openai.com
Homer City Energy CampusHomer City, PennsylvaniaThe 4.5 GW gas plant is being built to serve a data center campus, but the site also connects to the PJM and New York grids, and no source we could read says the campus load will bypass the grid.utilitydive.com
Talen Energy's Susquehanna campus for AmazonSalem Township, PennsylvaniaIt was the best-known behind-the-meter deal until it moved to a grid-delivered contract in April 2026, according to Talen's second-quarter 10-Q.sec.gov
Stargate Abilene on-site gas plantAbilene, TexasCrusoe told Floodlight the on-site turbines will be used only for backup, and an Oracle and OpenAI fact sheet says the campus connects directly to the Texas grid.texastribune.org
NTT Data's Osaka site for AnthropicOsaka, JapanNikkei reported the project was looking at on-site generation and fuel cells, but no plan has been announced.Our report
Meta's Hyperion campusRichland Parish, LouisianaIts new gas plants are being built through Entergy, the local utility, rather than by Meta on its own site.fortune.com

How this list is kept

A project gets a row when a company statement, a regulatory filing, or a news report we can read says its power comes from generation on its own site, from a direct connection to a power plant that doesn't run through the utility's grid, or from on-site power used until a grid connection arrives. A power purchase agreement alone doesn't qualify, and neither does a new plant that sells into the grid.

Every row was checked twice: once when it was found, and again by a second reader who reopened each source. Rows that rested only on an advocacy group, an aggregator, or a summary site were held back until a better source turned up. Where sources disagree on a plant's size or a date, the row says so.

The list is not a census. Smaller on-site systems, backup generators, and projects with no public filing are not here. We don't add up the megawatts, because the figures mix plant capacity, data center load, and campus plans.

Common questions

What does behind the meter mean for a data center?
It means the data center gets its electricity before it reaches a utility's meter: from a power plant on its own site, or over a direct line from a power station, instead of through the utility's grid. Some projects use on-site power only as a bridge until a grid connection is ready, and those are marked on this page.
Why are data centers building their own power plants?
Mainly to start sooner. Developers say a grid connection for a large data center can take years. RHAELM's chief executive said co-locating at JERA's Chiba power station would let the companies deliver a 400 MW facility years ahead of a conventional grid-connected timeline.
What is the largest behind-the-meter data center project?
By planned generation, Fermi America's Project Matador in Carson County, Texas, which describes about 11 GW of private-grid generation in its Nov. 12, 2026 quarterly filing. It has no signed tenant. The largest fully operating one on this page is the Socrates plants at Meta's New Albany, Ohio, campus, at 400 MW.
Does the Senate's data center grid cost bill cover behind-the-meter projects?
Not fully off-grid ones. The bill the Senate passed 62-33 on Nov. 19, 2026 defines a covered data center site as one supplied through equipment connected to the bulk-power system. A fully off-grid campus falls outside that definition. The passed text sets no megawatt threshold.
How often is this page updated?
Rows change when a project gets a permit, starts construction, comes online, or is canceled. Each change is checked against the filing, release, or report it links to.

Use this data

Our figures are free to reuse in articles, newsletters, and research with attribution and a link back to this page. Current table as a file: download CSV.

Suggested citation: AIStockWire, “Behind-the-meter data center tracker,” aistockwire.com/behind-the-meter-data-centers, data as of Nov 27, 2026. Questions about the data: support@aistockwire.com.

Related: Data center moratorium tracker, AI compute commitments, AI debt tracker. Not investment advice.