Behind-the-meter data center tracker
Data center projects that run on their own power plant, a direct line to a power station, or on-site bridge power, instead of waiting for a grid connection.
Updated · ledger as of Nov 27, 2026
More data center developers are building their own power instead of waiting years for a utility connection. This page lists each project we could confirm that gets its electricity behind the meter, with the companies involved, the plant's size, and where the project stands. Each row links to the filing, release, or report we read.
United States
Texas has the most projects on the list, followed by Ohio. Rows are sorted by status, then by size. Megawatt figures are what the source reports, and they don't all measure the same thing, so read the label under each one.
| Project | Power | Status | Source |
|---|---|---|---|
| Vantage San Antonio campusesSan Antonio, TexasVantage Data Centers, VoltaGridEnvironmental groups sued in federal court in September, saying the plants were split into smaller sources to qualify for less stringent permits. Their July notice put the gas plants at 423 MW, and the Sierra Club's September release says 405 MW. | 423 MW (405 MW in a later filing)Gas enginesOn-site plant | As of Sep 22, 2026 | Texas Public Radio Second source |
| Socrates (Meta New Albany)New Albany, OhioWilliams (WMB), Meta (META)Williams built and runs the two 200 MW plants for Meta. It said on Nov. 2 that Socrates was fully online and that the second site, Plato North, was on track for service by mid-November. | 400 MW across two sitesGas turbines and enginesOn-site plant | As of Nov 2, 2026 | Ohio Power Siting Board Second source |
| Equinix fuel cell fleet19 sites in six statesEquinix (EQIX), Bloom Energy (BE)About 75 MW was running and 30 MW was under construction as of February 2025. The fuel cells supplement grid power. | More than 100 MW in totalFuel cellsOn-site plant | As of Feb 20, 2025 | Bloom Energy |
| Redwood Energy and CrusoeSparks, NevadaRedwood Materials, CrusoeSolar power stored in old electric vehicle batteries runs a 2,000-GPU modular data center that Crusoe describes as off-grid. | 12 MW, 63 MWhSolar and used EV batteriesOn-site plant | As of Mar 24, 2026 | TechCrunch Second source |
| ECL MV1Mountain View, CaliforniaECL, LambdaThe Register reported a Lambda system there powered entirely by hydrogen fuel cells. | About 1 MWHydrogen fuel cellsOn-site plant | As of Sep 24, 2025 | Data Center Frontier Second source |
| Project Jupiter (Stargate New Mexico)Dona Ana County, New MexicoOracle (ORCL), Bloom Energy (BE)Bloom fuel cells replaced earlier plans for gas turbines and diesel generators. The hearing on the microgrid's state air permit was delayed again in November at the request of the developer and the state. | Up to 2,450 MWFuel cellsOn-site plant | Data center under construction; power permit pendingAs of Nov 6, 2026 | Our report Oracle Second source |
| Project Phoenix (Aligned)Shippingport, PennsylvaniaAligned Data CentersAligned broke ground on Sept. 10 at the former Bruce Mansfield coal plant. It hasn't named its fuel cell supplier or said how much grid capacity the site keeps for backup. | 2 GW campusGas-fed fuel cellsOn-site plant | Under constructionAs of Sep 10, 2026 | Data Center Frontier Second source |
| Joule campusMillard County, UtahJoule Capital Partners, Caterpillar (CAT)Joule told BloombergNEF that 455 MW is contracted for delivery by the end of 2026 and 1.5 GW by the start of 2028. The site's grid connection isn't big enough for the data center. | 1,500 MW first phaseGas enginesOn-site plant | Under constructionAs of Feb 27, 2026 | BloombergNEF Second source |
| Colossus 2 power plantSouthaven, MississippiSpaceX (SPCX)Sixty-nine temporary turbines power the site until the 41-turbine permanent plant is finished; SpaceX says the temporary units will be gone by July 2027. A federal judge let the NAACP's lawsuit over the turbines proceed on Oct. 30. | 1,200 MW plantGas turbinesOn-site plant | Under constructionAs of Jul 30, 2026 | Our report xAI Second source |
| Meitner Energy CenterGray and Roberts counties, TexasAlphabet (Google, Intersect) (GOOGL)Google says the data center will come online alongside dedicated power. The gas units for firming are on site, and their size wasn't disclosed. | More than 1 GW of renewablesWind, solar, batteries, and gasOn-site plant | Under constructionAs of Jun 4, 2026 | POWER Magazine Second source |
| Crusoe Abilene campus for MicrosoftAbilene, TexasCrusoe, Microsoft (MSFT)Crusoe says the campus pairs a 900 MW on-site power plant with batteries, and the first building is due to be energized in mid-2027. It hasn't said what fuel the plant uses. | 900 MW plantNot disclosedOn-site plant | Under constructionAs of Jun 9, 2026 | Crusoe Second source |
| Apollo (Meta Bowling Green)Wood County, OhioWilliams (WMB), Meta (META)Ohio's siting board approved the plant on Feb. 3, less than three months after plans were submitted, Reuters reported. The plant will serve only Meta. | 350 MW plus 120 MW of batteriesGas turbinesOn-site plant | Under constructionAs of Jun 16, 2026 | Ohio Power Siting Board Second source |
| Project Aquila (Meta Eagle Mountain)Eagle Mountain, UtahWilliams (WMB), Meta (META), GE Vernova (GEV)City planning minutes describe a 286 MW plant separated from Rocky Mountain Power's system. Williams has since said Aquila will supply 520 MW under a 12.5-year agreement. | 286 MW in city filingsGas turbines, engines, and batteriesOn-site plant | Under constructionAs of May 7, 2026 | Eagle Mountain Planning Commission Second source |
| Aalo microreactor and CrusoeIdaho National LaboratoryAalo Atomics, CrusoeA federal pilot program demonstration that plans to power a Crusoe modular data center in 2027. | 10 MW reactorSmall nuclear reactorOn-site plant | Under constructionAs of Jul 30, 2026 | POWER Magazine Second source |
| Frontier (Vantage, Stargate)Shackelford County, TexasVantage Data Centers, VoltaGrid, Oracle (ORCL)An Oracle and OpenAI fact sheet says the campus is powered by an on-site, behind-the-meter gas microgrid using Jenbacher engines. Bisnow reported the 10-building campus at 1.4 GW and more than $25 billion. | 1.4 GW campusGas enginesOn-site plant | Under constructionAs of Sep 4, 2026 | Oracle and OpenAI fact sheet Second source |
| GW RanchPecos County, TexasPacifico Energy, Amazon (AMZN)Amazon has confirmed it bought the site and plans to buy power from Pacifico, whose plant is designed to run off the grid. Amazon says it is exploring a later move to grid service, and the state's preliminary review describes a 5,000 MW plant. | 7,650 MW of gas in the air permitGas, solar, and batteriesOn-site plant | ApprovedAs of Aug 17, 2026 | Turbomachinery Magazine Second source |
| Monarch campus (Nscale)Mason County, West VirginiaNscale, Caterpillar (CAT), Anthropic (ANT)Caterpillar and its dealer are due to deliver gas generators from September 2026 through August 2027, reaching 2 GW in the first half of 2028. Anthropic plans to use a 460 MW building at the campus. | 2 GW of generators contractedGas enginesOn-site plant | State-certified microgridAs of Nov 2, 2026 | Our report Nscale Second source |
| CloudBurst San MarcosGuadalupe County, TexasCloudBurst Data Centers, Energy Transfer (gas supply) (ET)Texas regulators issued the plant's permit on Nov. 16, according to Public Citizen. The permit is in the name of Evolve Energy, which shares a chief executive with CloudBurst. Earlier reports described a 1,200 MW plant. | 1,605 MW in the state reviewGas turbines and fuel cellsOn-site plant | ApprovedAs of Nov 16, 2026 | Public Citizen Second source |
| Prometheus HyperscaleEvanston, WyomingPrometheus HyperscaleUinta County approved the permit in June, and a judge dismissed a challenge in August. The company says the campus will run as a fully islanded microgrid. | 1,250 MW initialGas engines and turbinesOn-site plant | County permit approvedAs of Oct 28, 2026 | Prometheus Hyperscale Second source |
| Project Hummingbird (IEP)Greene County, PennsylvaniaInternational Electric PowerThe county planning commission approved the first phase, including two gas turbines, in December 2025. No tenant has been named. | 944 MW (local reports: 900 to 910 MW)Gas combined cycleOn-site plant | ApprovedAs of Dec 17, 2025 | Utility Dive |
| Freestone Energy Center and CyrusOneFreestone County, TexasConstellation Energy (CEG), CyrusOneThe Texas utility commission approved the arrangement in May with conditions that let the data center load be curtailed. Constellation says CyrusOne signed for 380 MW, with another 380 MW in a second phase. | 760 MW loadGas plantWired to a power plant | ApprovedAs of May 2026 | Texas PUC Docket 58872 Second source |
| Starbase supercomputing siteStarbase, TexasSpaceX (SPCX)SpaceX says it will invest more than $24 billion. Reports of the plant's size conflict: the application describes 35 turbines and 748 MW, while Public Citizen, citing state records, says the permit covers 43 turbines and 1,456 MW. | 748 MW in the permit applicationGas turbinesOn-site plant | ApprovedAs of Nov 16, 2026 | Our report TechRadar Second source |
| AWS Hilliard fuel cellsHilliard, OhioAmerican Electric Power (AEP), Amazon (AMZN), Bloom Energy (BE)AEP says the fuel cells let data centers start while the grid grows. The city of Hilliard filed an appeal of the Ohio EPA permit in November 2025. | 72.9 MWFuel cellsBridge until grid | ApprovedAs of Sep 22, 2025 | AEP Ohio Second source |
| Cologix fuel cellsCentral OhioAmerican Electric Power (AEP), Bloom Energy (BE)Ohio regulators approved the 15-year contract on May 28, 2025. Cologix pays the full cost. | Not disclosedFuel cellsBridge until grid | ApprovedAs of May 28, 2025 | AEP Second source |
| Project Matador (Fermi America)Carson County, TexasFermi (FRMI)Fermi's Nov. 12 quarterly filing describes about 11 GW of planned private-grid generation and no signed tenant. Its hyperscaler deal is a non-binding letter of intent, and Texas Tech can end the land lease if it doesn't give a go-ahead by Dec. 31. | About 11 GW plannedGas now, nuclear plannedOn-site plant | ProposedAs of Nov 12, 2026 | Fermi 10-Q Second source |
| Project KilbyReeves County, TexasChevron (CVX), Microsoft (MSFT), GE Vernova (GEV), Texas Pacific Land (TPL)Chevron plans the plant to supply a Microsoft data center under a 20-year agreement, with first power targeted for 2028. It hasn't announced a final investment decision. | 2,670 MWGas turbinesOn-site plant | ProposedAs of Jun 23, 2026 | Oil & Gas Journal Second source |
| Project Horizon (Poolside)West TexasPoolside, CoreWeave (CRWV)CoreWeave is the anchor tenant for the first 250 MW phase under a 15-year lease. The grid connection is for backup. | 2 GW campus in eight phasesGas turbinesOn-site plant | ProposedAs of Oct 29, 2025 | Data Center Frontier |
| Comanche Peak and AmazonSomervell County, TexasVistra (VST), Amazon (AMZN)Vistra's filing with the Texas utility commission says the Amazon load connects to the nuclear plant and is not expected to be served by grid power. Vistra's 10-Q calls it a 20-year, 1,200 MW deal starting in the fourth quarter of 2027. | 1,200 MW loadNuclear plantWired to a power plant | Awaiting state approvalAs of Nov 25, 2026 | Texas PUC Docket 59399 Second source |
| PowerPlay AI and Sharon AIAbilene area, TexasPowerPlay AI, Sharon AI (SHAZ)The joint venture is still lining up gas supply and choosing a power producer. | 400 MW targeted by 2028Gas (type not chosen)On-site plant | ProposedAs of Jul 20, 2026 | PowerPlay AI Second source |
| McCloud Generation (Meta El Paso)El Paso, TexasEl Paso Electric, Meta (META)The utility-owned plant would power the data center alone for five years, starting in 2027, and stay separate from El Paso Electric's transmission system. Meta pays the costs. We found no ruling yet from the state utility commission. | 366 MWGas enginesBridge until grid | ProposedAs of Apr 6, 2026 | Argus Media Second source |
| CoreWeave in VoloVolo, IllinoisCoreWeave (CRWV), Bloom Energy (BE)Bloom said the fuel cells would be commissioned in the third quarter of 2025. We found no confirmation that they were. | Not disclosedFuel cellsOn-site plant | ProposedAs of Jul 16, 2024 | Bloom Energy Second source |
| Intel Santa Clara expansionSanta Clara, CaliforniaIntel (INTC), Bloom Energy (BE)Intel's site has run on Bloom fuel cells since 2014, and the 2024 deal expands it. We found no report that the expansion is finished. | Not disclosedFuel cellsOn-site plant | ProposedAs of May 9, 2024 | Bloom Energy |
Outside the US
The Japanese and South Korean projects take power directly from a power plant or wind farm. Most of the Canadian and Australian ones are new gas plants built for the campus.
| Project | Power | Status | Source |
|---|---|---|---|
| SK AI data center UlsanUlsan, South KoreaSK Telecom, Amazon (AMZN)SK Multi Utility, a local power provider, supplies electricity directly instead of the national utility, which serves as backup. The first 41 MW building is due by the end of 2027. | 100 MW of data center by 2029District power plantWired to a power plant | Under constructionAs of Sep 13, 2026 | Asia Economy Second source |
| Pure DC Dublin microgridWest Dublin, IrelandPure Data Centres, WartsilaWartsila says the microgrid is designed to run completely independently from the national grid. Its first two energy centers, 30 MW each, were being commissioned. | 60 MW built, 110 MW plannedGas enginesOn-site plant | Being commissionedAs of Mar 12, 2026 | Microgrid Knowledge Second source |
| Greenlight Electricity Centre (Meta Alberta)Sturgeon County, AlbertaPembina Pipeline (PBA), Meta (META)Pembina calls Greenlight a dedicated, behind-the-meter plant for Meta's data centre. It says the plant has all major regulatory approvals and is due in service in the second half of 2030. | 932 MWGas combined cycleWired to a power plant | Approved; investment decision madeAs of Jul 8, 2026 | Our report Pembina Second source |
| Cloud Carrier Southern HighlandsMoss Vale, AustraliaCloud CarrierA second 16 MW unit was refused and is in court, and a separate state application seeks about 673 MW of gas generators to power the campus. | 14 MW approvedGas generatorsOn-site plant | 14 MW approved; more in court or proposedAs of Oct 7, 2025 | RenewEconomy Second source |
| Herbata campusNaas, IrelandHerbataKildare County Council approved the campus in August 2025, and appeals lodged in September 2025 show no decision on the planning board's case page. An on-site gas plant would supply half its electricity, with wind and solar contracts covering the rest. | Not disclosedGasOn-site plant | Council approved; appeal pendingAs of Aug 20, 2025 | The Irish Times Second source |
| Shelford data centre (Era4)Canterbury, EnglandEra4The site would take power by private wire from a landfill gas plant next door, with the national grid as backup. The council approved it on Oct. 15 by four votes to one, with three abstentions. | Not disclosedLandfill gas plantWired to a power plant | ApprovedAs of Oct 15, 2026 | Construction Review Online Second source |
| Wonder Valley (O'Leary Digital)Greenview, AlbertaO'Leary DigitalThe developer plans to file for provincial utility approval of the gas plant by the end of 2026. Sturgeon Lake Cree Nation has filed three court challenges. | 7.5 to 9 GW, by reportGasOn-site plant | ProposedAs of Nov 3, 2026 | BNN Bloomberg Second source |
| Beetaloo Digital WeddellNear Darwin, AustraliaBeetaloo EnergyThe territory government made an exclusive commitment of more than 185 hectares of land to the project, which the company says could attract A$40 billion of investment. | Up to 2 GWGasOn-site plant | ProposedAs of Jul 22, 2026 | ESD News Second source |
| Project Ares (Energy North)Northern Territory, AustraliaEnergy NorthThe developer plans a fully off-grid campus that starts mainly on gas. A final investment decision is targeted 12 to 18 months after approvals. | About 1,038 MW of gasGas, solar, and batteriesOn-site plant | Under environmental assessmentAs of Jul 22, 2026 | The Next Web Second source |
| JERA Chiba power stationChiba, JapanJERA, Dell (DELL), RHAELM, Apollo (APO)JERA's Oct. 1 release says the project will draw power behind the meter from its operating plant, with investment expected to exceed $15 billion. JERA said on Nov. 27 it is in talks with Anthropic, Meta, and others about sites at its Tokyo-area plants. | Up to 400 MWThermal power plantWired to a power plant | ProposedAs of Oct 1, 2026 | Our report JERA Second source |
| SGC AI data center GunsanGunsan, South KoreaSGC Energy, KT CloudSGC Energy plans to connect its power plant directly to the data center and keep access to the national grid. Asia Economy reported that full operation is slated for the first quarter of 2028. | 60 MW first phase, up to 300 MWPower plantWired to a power plant | ProposedAs of Sep 28, 2026 | Herald Business Second source |
| Toyota Tsusho wind-farm data centerWakkanai, JapanToyota TsushoPower comes by private line from a 42 MW wind farm, not through the utility grid. Full operation is planned within 2027. | 3 MWWind farmWired to a power plant | ProposedAs of Jan 14, 2026 | Toyota Tsusho |
The Senate bill on data center grid costs
The Senate passed the Bipartisan American Affordability and Jobs Act 62-33 on Nov. 19, 2026, according to the roll call. The bill would make data centers pay the grid costs they cause instead of other customers. It now goes back to the House, which has to act on the Senate's version.
The cost rules reach a data center site that is "supplied through electrical equipment that is connected to the bulk-power system," the passed text says. A campus that runs fully off the grid falls outside that definition. Some coverage of the bill described a 20 MW threshold, but the passed text sets none.
Projects we left out, and why
These projects are often described as behind the meter. The sources we read don't support that today.
| Project | Why it isn't listed | Source |
|---|---|---|
| SB Energy's Ports-Pike campus for OpenAIPike County, Ohio | Power comes through AEP Ohio's grid. OpenAI says the first 800 MW will largely use existing AEP infrastructure. | openai.com |
| Homer City Energy CampusHomer City, Pennsylvania | The 4.5 GW gas plant is being built to serve a data center campus, but the site also connects to the PJM and New York grids, and no source we could read says the campus load will bypass the grid. | utilitydive.com |
| Talen Energy's Susquehanna campus for AmazonSalem Township, Pennsylvania | It was the best-known behind-the-meter deal until it moved to a grid-delivered contract in April 2026, according to Talen's second-quarter 10-Q. | sec.gov |
| Stargate Abilene on-site gas plantAbilene, Texas | Crusoe told Floodlight the on-site turbines will be used only for backup, and an Oracle and OpenAI fact sheet says the campus connects directly to the Texas grid. | texastribune.org |
| NTT Data's Osaka site for AnthropicOsaka, Japan | Nikkei reported the project was looking at on-site generation and fuel cells, but no plan has been announced. | Our report |
| Meta's Hyperion campusRichland Parish, Louisiana | Its new gas plants are being built through Entergy, the local utility, rather than by Meta on its own site. | fortune.com |
How this list is kept
A project gets a row when a company statement, a regulatory filing, or a news report we can read says its power comes from generation on its own site, from a direct connection to a power plant that doesn't run through the utility's grid, or from on-site power used until a grid connection arrives. A power purchase agreement alone doesn't qualify, and neither does a new plant that sells into the grid.
Every row was checked twice: once when it was found, and again by a second reader who reopened each source. Rows that rested only on an advocacy group, an aggregator, or a summary site were held back until a better source turned up. Where sources disagree on a plant's size or a date, the row says so.
The list is not a census. Smaller on-site systems, backup generators, and projects with no public filing are not here. We don't add up the megawatts, because the figures mix plant capacity, data center load, and campus plans.
Common questions
- What does behind the meter mean for a data center?
- It means the data center gets its electricity before it reaches a utility's meter: from a power plant on its own site, or over a direct line from a power station, instead of through the utility's grid. Some projects use on-site power only as a bridge until a grid connection is ready, and those are marked on this page.
- Why are data centers building their own power plants?
- Mainly to start sooner. Developers say a grid connection for a large data center can take years. RHAELM's chief executive said co-locating at JERA's Chiba power station would let the companies deliver a 400 MW facility years ahead of a conventional grid-connected timeline.
- What is the largest behind-the-meter data center project?
- By planned generation, Fermi America's Project Matador in Carson County, Texas, which describes about 11 GW of private-grid generation in its Nov. 12, 2026 quarterly filing. It has no signed tenant. The largest fully operating one on this page is the Socrates plants at Meta's New Albany, Ohio, campus, at 400 MW.
- Does the Senate's data center grid cost bill cover behind-the-meter projects?
- Not fully off-grid ones. The bill the Senate passed 62-33 on Nov. 19, 2026 defines a covered data center site as one supplied through equipment connected to the bulk-power system. A fully off-grid campus falls outside that definition. The passed text sets no megawatt threshold.
- How often is this page updated?
- Rows change when a project gets a permit, starts construction, comes online, or is canceled. Each change is checked against the filing, release, or report it links to.
Use this data
Our figures are free to reuse in articles, newsletters, and research with attribution and a link back to this page. Current table as a file: download CSV.
Suggested citation: AIStockWire, “Behind-the-meter data center tracker,” aistockwire.com/behind-the-meter-data-centers, data as of Nov 27, 2026. Questions about the data: support@aistockwire.com.
Related: Data center moratorium tracker, AI compute commitments, AI debt tracker. Not investment advice.