AI GPU arrives in weeks. The power gear behind it takes years: GE Vernova (GEV), Vertiv (VRT), Eaton (ETN), Quanta (PWR) and Powell (POWL)

AI data center GPU connected to transformers, switchgear, a gas turbine and the power grid

AI-generated illustration of the power infrastructure supporting an AI data center

Key points

  • The toughest part of expanding AI infrastructure is no longer obtaining the chip. The bottleneck has shifted to electricity and the physical systems required to produce that power and deliver it to a server rack.
  • Orders for new heavy-duty gas turbines now stretch years into the future, while a large power transformer may require two to three years to manufacture. Those delivery schedules form the core of the investment argument for this group.
  • This page maps the public companies that sell into the shortage: GE Vernova, Vertiv, Eaton, Quanta Services, Powell Industries, nVent, Hubbell and MasTec, with what each one makes and how big its order book has gotten.
  • For the power that actually gets generated, the nuclear, gas, and solar names, see our separate AI power piece. Any ticker here can be run through our stock score tool.

For most of the past two years, investors treated AI primarily as a semiconductor trade. That framing no longer captures the whole buildout. An Nvidia (NVDA) GPU can arrive before the power needed to operate it, and that mismatch increasingly determines when a data center is able to open.

The scale of the demand is difficult to miss. US data centers consumed roughly 192 terawatt-hours of electricity in 2024, equal to 4.7% of national use. Lawrence Berkeley National Laboratory projects that the share could reach between 9.5% and 15% by 2030. Power prices have moved alongside that demand. PJM, the grid operator serving 13 states, holds an annual auction for future generating capacity. Its clearing price climbed from $28.92 per megawatt-day for 2024 to 2025 to $329.17 for 2026 to 2027. Analysts say data center demand explains most of the increase.

Even when the money is there, the wait is long. About 2,300 gigawatts of power projects were sitting in interconnection queues at the end of 2024, and the typical project now takes more than four years to connect, according to Berkeley Lab. New gas turbines are booked out further than that.

We've already covered the companies that generate the power, the ones behind why electricity became the binding constraint on the whole trade. This piece is about the layer in between: the turbines, transformers, switchgear and crews that carry electrons the last mile to the rack. It's a less crowded corner of the AI trade, and the order books show why.

What each company sells

Eight public names cover most of this layer. The first column is what they make for a data center. The second is the size of the order book each one last reported.

CompanyWhat it sells into a data centerOrder book, as reported
GE Vernova (GEV)Gas turbines, grid transformers, high-voltage switchgear$176B total backlog; 116 GW of gas orders and slot reservations (Q2 2026)
Vertiv (VRT)Power distribution, UPS, and liquid cooling at the rackAbout $15B backlog (end of 2025)
Eaton (ETN)Electrical switchgear, busway, power distributionRecord backlog about $24B; data-center revenue up 65% (Q2 2026)
Quanta Services (PWR)Builds the transmission lines and substations that feed the siteRecord backlog $53.4B (Q2 2026)
Powell Industries (POWL)Custom switchgear and electrical systemsRecord backlog $2.4B, including a single data-center award over $400M (2026)
nVent Electric (NVT)Enclosures, racks and liquid-cooling hardwareSales up 53%, backlog about $2.5B (Q2 2026)
Hubbell (HUBB)Grid and utility components, connectors, enclosuresBought DMC Power for $825M to push into data-center power
MasTec (MTZ)Builds power-delivery infrastructure18-month backlog $21.4B (Q2 2026)

Each backlog number comes from the company's latest report. Because the totals change from quarter to quarter, they should be read as a snapshot rather than a live tally.

The order book creates the advantage

The clearest case is GE Vernova. It spun out of General Electric in 2024 and now sells the three things a new data center campus needs most: gas turbines, grid transformers and high-voltage switchgear. On its July 2026 report the company said gas-equipment orders and paid slot reservations had reached 116 gigawatts, and that it was already taking reservations for turbine deliveries in 2031. A new heavy-duty turbine order placed today lands four to five years out.

The transformer wait is nearly as long. Wood Mackenzie put large power transformer lead times above two years in 2024, up from under one year in 2021. Medium-voltage switchgear has stretched too. When a piece of equipment takes years to arrive, the company holding the order book is selling something a rival can't simply undercut on price.

That is why a backlog matters more here than in most of the market. An order book that runs into 2029 or 2031 is revenue these companies can already see, which is rare for industrial equipment. It's also why several of these stocks stopped trading like slow utilities and started trading like AI names.

What could go wrong

A reserved production slot is not the same as delivered equipment. A slowdown in AI construction could lead customers to postpone or cancel early orders and reservations before they become shipments. If that happens, today's apparently durable backlogs would begin to shrink. Every company in the table carries that risk.

Price is the other problem. Several of these stocks already carry years of growth in the multiple. GE Vernova and Vertiv have both sold off hard on quarters that looked fine on the surface, because the bar Wall Street set was higher than the print. And this is still cyclical, capital-heavy equipment, where margins swing with steel, copper, and labor. A long backlog lowers the risk. It does not remove it.

None of this makes the group a buy or a sell. It maps where a data center dollar goes once it leaves the chip budget. Every name above links to its live SEC filings, and our stock score tool grades each one's actual numbers, profits, debt, insider activity, and dilution, in about ten seconds.

Sources

  • Related coverage: AI's power problem, and the generation stocks behind it
  • Related coverage: Inside the AI hardware stack, layer by layer
  • Lawrence Berkeley National Laboratory, United States Data Center Energy Usage Report: 2025 Update
  • PJM, Base Residual Auction results (capacity auction clearing prices)
  • Lawrence Berkeley National Laboratory, Queued Up 2025 edition (interconnection queue data)
  • GE Vernova, second-quarter 2026 results (July 2026)
  • Wood Mackenzie, power transformer lead-time analysis
  • Company backlog figures from each firm's most recent quarterly report, via SEC EDGAR

This is general market commentary and opinion, not investment advice. Markets can go down as well as up, and you can lose money. Always do your own research and consider speaking with a licensed financial professional before making any investment decision.

Frequently asked questions

Which stocks benefit from AI data center power demand?

The AI power trade splits into two layers. One is the companies that generate electricity, the nuclear, gas and solar names. The other is the equipment layer that delivers it: GE Vernova (GEV) for turbines and grid gear, Vertiv (VRT) and Eaton (ETN) for power distribution and switchgear, Powell Industries (POWL) for custom switchgear, and Quanta Services (PWR) and MasTec (MTZ) for building the transmission lines and substations. nVent (NVT) and Hubbell (HUBB) round out the group. This is general market commentary and not investment advice.

Why are gas turbines and transformers a bottleneck for AI data centers?

Because they take years to build, not weeks. GE Vernova said in July 2026 that it was already taking reservations for gas-turbine deliveries in 2031, and new orders now stretch four to five years out. Large power transformers passed two-year lead times in 2024, up from under a year in 2021, according to Wood Mackenzie. A data center can install its chips long before the grid equipment to power them arrives, which is why electricity, not silicon, now sets the pace of the buildout.

What does GE Vernova (GEV) sell to data centers?

GE Vernova makes three of the things a data center campus needs most: gas turbines to generate power, large transformers to step voltage up and down, and high-voltage switchgear to distribute it. It spun out of General Electric in 2024. On its second-quarter 2026 report the company said its total backlog had reached $176 billion, with 116 gigawatts of gas-equipment orders and paid slot reservations. This is general market commentary and not investment advice.

Is Vertiv (VRT) a power stock or a cooling stock?

Both, which is what makes it a pure play on the data center itself. Vertiv sells the power distribution, UPS systems and busway that move electricity inside the building, and it also sells the liquid cooling that keeps dense AI racks from overheating. That puts it in the middle of two shortages at once. It ended 2025 with a backlog of about $15 billion.

Are AI power equipment stocks risky?

Yes. The order books are large, but a reservation is not a delivered order, and a slowdown in AI spending could see backlogs canceled or delayed. Several of these stocks also already price in years of growth, so they can fall hard on a quarter that merely meets expectations. The business is cyclical and capital-heavy, with margins that move on steel, copper and labor costs. This is general market commentary and not investment advice.

More on ETN and GEV

Dennis Singleton
Dennis Singleton

Dennis Singleton has spent years following the markets, but what keeps his attention is how AI is built. He writes about the companies behind the technology, from semiconductor designers and advanced packaging to photonics, memory, networking, and the hardware powering modern AI. His approach starts with filings, earnings, and industry research, then translates the important details into clear, straightforward analysis without unnecessary hype.